27th June update

27th June update

Welcome to another update on the development of the new Cornerstone Centre at St John’s in Edinburgh! The first few photos below show the storage space behind the first retail unit, along with the soon to be completed retail

16th June update

16th June update

The latest news update to share is that the building works in the retail units have been almost completed all bar a few minor things that need tidying up! The new security doors look great and the lighting really modernises the new

25th May update

25th May update

The building works on the Terrace level feels like it is going much quicker in the last couple of weeks, but as the Site Manager pointed out; this is often the case in the final stages as there’s more happening that is visible. As you can see

10th May update

10th May update

It’s been a couple weeks since we last provided an update about the build at Cornerstone Centre St John’s but lots has happened in the past couple of weeks; the electricians, plumbers, plasterers and carpenters are all racing

28th February update

28th February update

This week was interesting to see the new partition walls going up in the terrace area, with the new cafe and shops taking shape. The first photo shows one of the new walls. The second