10th May update

10th May update

It’s been a couple weeks since we last provided an update about the build at Cornerstone Centre St John’s but lots has happened in the past couple of weeks; the electricians, plumbers, plasterers and carpenters are all racing

24th April update

24th April update

The biggest change this week comes from the new archway/entrance being built on the west side of the main hall. The stones that had previously been knocked down when the west wall was demolished are being reused and in

17th April update

17th April update

Someone commented recently that building projects are like mushrooms; little seems to happen at first, then all of a sudden things gather pace. And that’s how the Cornerstone Centre has been so far.

27th March update

27th March update

This week things really seemed to jump ahead with the removal of a whole section of flooring between the Hall and basement! it really opens things up, but won’t stay that way for long. The cement

14th March update

14th March update

The latest news from the development is that the builders are preparing to break through the final section of the archway from the Hall into the basement below. The drain pipe you

28th February update

28th February update

This week was interesting to see the new partition walls going up in the terrace area, with the new cafe and shops taking shape. The first photo shows one of the new walls. The second