20th November update

20th November update

Two weeks since the last update but the Cornerstone Centre refurbishment is as we always say really coming along. The last time I visited the foundations for the staircase had been installed and today the stairs are there. The welders

1st November update

1st November update

The biggest change this week comes from the new archway/entrance being built on the west side of the main hall. The stones that had previously been knocked down when the west wall was demolished are being reused and in

29th September Update

29th September Update

Welcome to the latest update on the Cornerstone Centre. The last couple of weeks have seen the slate roofing works complete, the steel frame and block work for the new lift finished, as well as the outside finishes for the new Hall

13th September update

13th September update

If you were to take a look around the development today, you’d be struck by how much of a difference a week can make! Downstairs, the One World Shop’s own shop fitters have commenced their work with their new

7th September update

7th September update

Welcome to the latest update on our Cornerstone Centre development. With the festival period over, the lower terrace has been cleared of the stalls and food and drink stands. Cornerstone Bookshop has been attracting a steady

18th August update

18th August update

Cornerstone Centre august 2017 update. The latest news about the building works is that is now appears we will be getting the keys from the contractors in November. This is a slight delay on what we had hoped for, but is