23rd February update

23rd February update

Big transformations in our Cornerstone Centre update this week. As you’ll notice we’re capturing one set of photos this week and Chris our photographer visited last Friday. Today in the main

17th February update

17th February update

This week’s Cornerstone Centre update has a few things going on. First of all the west Wall is really going up, it looks really great. The builders are taking old pieces of stone and building this into a

8th February update

8th February update

The biggest developments within the Cornerstone Development’s site are down in the basement, or the old cafe, whatever you want to call it. The area where the lift is being installed is being

2nd February update

2nd February update

The biggest change this week comes from the new archway/entrance being built on the west side of the main hall. The stones that had previously been knocked down when the west wall was